Aluminum Factory, Anode Production Hall

status:

is finished

contract type:

c

project domain:

industry

location:

Iran , Markazi

Aluminum Factory, Anode Production Hall
Contract Type Construction
Location Arak, Iran
Executive stage Under Construction
Commencement Date Nov., 2019
Initial Duration 14 months
General works’ Quantity
Earth works 61,000 m³
concreting 12,000 m³
Reinforcement 680 tons
Form working 19,000 m²
Metal works 1,000 tons

 

Brief Description

Regarding the need to Anode for Iran Aluminum Factory (IRAELCO), a specific plan for implementing an anode production hall has been developed near Arak city in Iran. The factory nominal capacity is 35,000 ton per year.

 

Technical Specifications

BolandPayeh work scope is to construct an industrial warehouse with an area of 6,500 square meters. The execution activities consist of excavation, foundation of the building, production hall, foundation of the equipment, concrete, metal, sealing, roof and its final cover, mechanical and electrical works.