| Contract Type | Construction |
| Location | Birjand, Iran |
| Executive stage | Final Hanover |
| Physical Progress | 100% |
| Commencement Date | Jun., 11, 2006 |
| Initial Duration | 14 months |
| General works’ Quantity | |
| Earth works | 52,000 m³ |
| concreting | 35,000 m³ |
| Reinforcement | 5,000 tons |
| Form working | 20,000 m² |
| Sliding formwork | 26,000 m² |
| Metal works | 1,500 tons |
Brief Description & Technical Specification
BolandPayeh service in this project is to construct a cement factory with a capacity of 3,000 tons per day which consists of clinker silos, clinker feed systems, clinker feeders, cement mills, cement silos, cement transfer system and loading building.