| Contract Type | Construction |
| Location | Masjed Soleiman, Iran |
| Executive stage | Final Hanover |
| Physical Progress | 100% |
| Commencement Date | Nov., 9, 1993 |
| Initial Duration | 30 months |
| General works’ Quantity | |
| Earth works | 100,000 m³ |
| concreting | 15,000 m³ |
| Reinforcement | 2,000 tons |
| Form working | 35,000 m² |
| Metal works | 1,000 tons |
Brief Description & Technical Specification
BolandPayeh service in this contract is to construct a cement factory with a total capacity of 3,000 tons per day.