Contract Type | Construction |
Location | Masjed Soleiman, Iran |
Executive stage | Final Hanover |
Physical Progress | 100% |
Commencement Date | Nov., 9, 1993 |
Initial Duration | 30 months |
General works’ Quantity | |
Earth works | 100,000 m³ |
concreting | 15,000 m³ |
Reinforcement | 2,000 tons |
Form working | 35,000 m² |
Metal works | 1,000 tons |
Brief Description & Technical Specification
BolandPayeh service in this contract is to construct a cement factory with a total capacity of 3,000 tons per day.