Contract Type | Construction |
Location | Tehran, Iran |
Executive stage | Final Handover |
Physical Progress | 100% |
Commencement Date | Feb., 5, 1995 |
Initial Duration | 20 months |
General works’ Quantity | |
Earth works | 18,000 m³ |
concreting | 9,000 m³ |
Reinforcement | 500 tons |
Form working | 20,000 m² |
Metal works | 70 tons |
Brief Description &Technical Specification
Chemistry faculty of Shahed University, is located in the southern Tehran, near Imam Khomeini holy shrine. BolandPayeh scope of work in this project was construction, procurement and installation of architectural, mechanical and electrical materials and equipment. Using exposed concrete methodology to construct 16 columns with a hexagonal shape of 1-meter diameter is the main feature of this project.